LTM tenders of Satkhira district. |
OSTETM tenders of Satkhira zilla. |
OTM tenders of Satkhira. |
View All the active tenders of Satkhira district.
eGP Tender ID: 732436; Works (NCT)
APP ID: 185649;
District: Satkhira
Package Title: Re-Sectioning of Embankment at Katakhali, Assasuni from Km 28.000 to Km 31.700 equal to 3.700 Km in Polder No-01 & Ghusuri, Kaliganj from km 52.200 to Km 59.000 equal to 6.800 Km in Polder No-03 Total 10.500 Km in C/W Drainage Improvement of Polder 1 2 6-8 and 6-8 (Extension) in Satkhira District under Satkhira O&M Division-1, BWDB, Satkhira during the year 2022-23.
Organization: Bangladesh Water Development Board (BWDB)
Procuring Entity: Satkhira O&M Division-1
Procurement Method: Open Tendering Method (OTM)
IFT Published on: 2022-10-04 15:20:00
Document last selling: 2022-11-02 14:00:00
Closing / Opening: 2022-11-03 09:00:00
Brief Description of Package: Re-Sectioning of Embankment at Katakhali, Assasuni from Km 28.000 to Km 31.700 equal to 3.700 Km in Polder No-01 & Ghusuri, Kaliganj from km 52.200 to Km 59.000 equal to 6.800 Km in Polder No-03 Total 10.500 Km in C/W Drainage Improvement of Polder 1 2 6-8 and 6-8 (Extension) in Satkhira District under Satkhira O&M Division-1, BWDB, Satkhira during the year 2022-23.
Tender Document Price: Tk. 4000;
Tender Security: 1200000 BDT
Official Cost Estimate (Prediction):
* Since document price is Tk. 4000, estimated cost should be more than 2 crore BDT.
* Tender Security can be maximum 3% of Official Cost Estimate. So estimated cost is more than Tk. 40000000.
* Tender Security is normally more than 1% of Official Cost Estimate. So estimated cost should be less than 120000000 BDT.
Thus, Official Cost Estimate should be BDT. 40000000 ~ 120000000.
Eligibility criteria:
Payment may require more than two years. No claim of interest for delaying of payment will be entertained.
Quantity of tender items may increase or decrease.
Prework or Postwork will be taken by taskforce and BWDB's concern engineer in charge. Final payment will be made on the measurement taken by taskforce.
The selected contractor will hand over total work site at a time. No scope to handover site partly.
TaskforceGuidelines will be considered as a part of contract.
The contractor will bear the expense to remove of illegal occupancy/structure if remain besides the embankment
Cost of interim and post work survey and video beyond schedule (if applicable) will be borne by contractor.
The design may be changed/altered/revised.
All the liability of contractor personnel will be borne by contractor.
Contract will be terminated if contractor's personnel is involved in any kind of unauthorized/illegal financial transaction from the locals during work implementation
Project: Drainage Improvement of Polder 1, 2, 6-8 & 6-8 (Extention) in Satkhira District.
Location of work / delivery: Sathkhira Sadar, Kaliganj, Asasuni
Budget Type: Development
Category: Engineering works and construction works; Works for complete or part construction and civil engineering work;
PE Address: Satkhira, City: Satkhira, Thana: Satkhira Sadar, District: Satkhira - 9400, Country: Bangladesh,