eGP Tender ID: 1181028; Works (NCT)
APP ID: 217024;
District: Satkhira
Reference No.: 1T-4/392, dated:19-11-2025
Package Title: Repair of Embankment (length 2.655 km) damaged due to Cyclone "Remal" at different locations of Polder No-1, 3 & 5 in Satkhira District Under Satkhira WD Division-1, BWDB, Satkhira.
Organization: Bangladesh Water Development Board (BWDB)
Procuring Entity: Satkhira WD Division-1
Procurement Method: Open Tendering Method (OTM)
IFT Published on: 2025-11-23 16:00:00
Document last selling: 2025-12-21 17:00:00
Closing / Opening: 2025-12-22 16:00:00
Brief Description of Package: DRMEP/Sat-1/03
Repair of Embankment (length 2.655 km) damaged due to Cyclone "Remal" at different locations of Polder No-1, 3 & 5 in Satkhira District Under Satkhira WD Division-1, BWDB, Satkhira.
Tender Document Price: Tk. 4000;
Tender Security: 2000000 BDT
Official Cost Estimate (Prediction):
* Since document price is Tk. 4000, estimated cost should be more than 2 crore BDT.
* Tender Security can be maximum 3% of Official Cost Estimate. So estimated cost is more than Tk. 66666666.
* Tender Security is normally more than 1% of Official Cost Estimate. So estimated cost should be less than 200000000 BDT.
Thus, Official Cost Estimate should be BDT. 66666666 ~ 200000000.
Eligibility criteria:
1) All tenderer must be registered in e-gp portal system.
2) Payment will be made upon availability of fund; no claim will be entertained.
4) VAT & IT from bill will be deducted as per prevailing Government Rate.
5) If any type of Structure/Obstrucle is needed to dismantle to execute the work as per Design & Specification, the tenderer will do this at his own expense.No extra claims will be considered.
6) The tenderer must follow the latest instructions and formats of CPTU.
7) If BWDB owned land is not sufficient to execute the work as per design & Specification, the bidder will do this at his own expense and planning.
8) It is mandatory to submit video and still photographs of the said work in pre-work and post work condition to PE at contractor'sown cost.
9) The design may be changed/altered/revised (if required) and quantity of tender item may be increased or decreased.
10) Cost of pre work, interim and post-work survey will be borne by the contractor.
11) The work must be executed as per approved design uploaded at tender document.
12) The approved taskforce guideline and Latest Technical specification for civil work of BWDB will govern provided in particular specifications.
13) In addition to BWDB, the consultant of DRMEP project will monitor and check the quality and quantity of executed work.
14) Tenderer/Firm must sign and submit duly filled-in ‘JICA’s Acknowledgement of Compliance (Form ACK) and must state itsfinancial situation in accordance with the Form FIN-1 of JICA’s Bidding Document uploaded at Sec-7 of tender document as per ITT 4.4 and ITT 5.5 respectively.
*** Once the Disaster Risk Management Enhancement Project (Component-1, BWDB Part) (2nd Revised) DPP is approved, the NOA will be Issued.
Project: Disaster Risk Management Enhancement Project (Component-1, BWDB Part)
Location of work / delivery: debhata, kaliganj, shyamnagar, Satkhira
Budget Type: Development
Development Partner: Japan International Cooperation agency(JICA)
Category: Construction work for water projects; Works for complete or part construction and civil engineering work;
PE Address: BWDB, Satkhira, City: Satkhira, Thana: Satkhira Sadar, District: Satkhira - 9400, Country: Bangladesh,
See more tenders from
Satkhira WD Division-1; Bangladesh Water Development Board (BWDB):
1280469 : W Sat-1/20/Remaining Work
Permanent Protective work with rehabilitation of Embankment of Length 0.415 from km 26.105 to km 26.520 of Polder No. 15 at Gabura under "Rehabilitation of polder-15 at Satkhira District (1st Revised)" Project
1280468 : W Sat-1/19/Remaining Work
Permanent Protective work with rehabilitation of Embankment of Length 0.210 from km 25.690 to km 25.900 of Polder No. 15 at Gabura under "Rehabilitation of polder-15 at Satkhira District (1st Revised)" Project.
1276443 : NDR Sat1/P-45/2025-26
Supply, Filling & Placing/Dumping of 11000 nos. 175 kg Polyster Geotextile bag for Emergency Flood Fighting at various places of Satkhira District as per instruction of Engineer in charge under Satkhira WD Division-1.
1276441 : NDR Sat1/P-43/2025-26
Supply and Installation of regulator gates (shutters), along with the related mechanical components, as part of the repair and maintenance of various regulators Under Operation Budget during the FY 25-26.
1276436 : NDR Sat1/P-38/2025-26
Temporary bank Protection Work from ch. Km 104.330 to 104.380 = 0.050 Km of Polder No-5 at Nildumur BGB camp Under Operation Budget of Shyamnagar Upazila in Satkhira District during the FY 25-26.
1195467 : NDR Sat1/P-24/2025-26
Repair of Embankment along with Temporary Slope Protection Work (1) from ch. Km 34.604 to 34.634=0.030 Km at Noikathi (2) from ch. Km 35.180 to 35.210=0.030 Km at Astakhali (3) from ch. Km 43.225 to 43.265=0.040 Km at Sholkhali Total 0.100 Km of Polder No-5 Under Operation Budget of Shyamnagar Upazila in Satkhira District during the FY 25-26.