Login |Register

LTM tenders of Bagerhat district. | OSTETM tenders of Bagerhat zilla. | OTM tenders of Bagerhat. | View All the active tenders of Bagerhat district.

eGP Tender ID: 871291; Works (NCT)
APP ID: 197056; District: Bagerhat
Reference No.: ET/BAG/3725; Date: 05/09/2023
Package Title: Construction of Flushing Cum Drainage Outlet at Km.45.760 of Polder-35/1 under Coastal Embankment Improvement Project (CEIP), Phase-1 as deposit work under Bagerhat O&M Division, BWDB, Bagerhat during the year 2022-23 & 2023-24. (Package No.- CEIP-1/DS/P35/1/DPM-9/6-19)
Organization: Bangladesh Water Development Board (BWDB)
Procuring Entity: Bagerhat O&M Division
Procurement Method: Open Tendering Method (OTM)
IFT Published on: 2023-09-10 20:30:00
Document last selling: 2023-09-24 16:00:00
Closing / Opening: 2023-09-25 13:15:00
Brief Description of Package: Construction of Flushing Cum Drainage Outlet at Km.45.760 of Polder-35/1 under Coastal Embankment Improvement Project (CEIP), Phase-1 as deposit work under Bagerhat O&M Division, BWDB, Bagerhat during the year 2022-23 & 2023-24. (Package No.- CEIP-1/DS/P35/1/DPM-9/6-19)
Tender Document Price: Tk. 2000; Tender Security: 500000 BDT
Official Cost Estimate (Prediction):
* Since document price is Tk. 2000, estimated cost should be more than 50 lacs BDT, but less than or equal 2 crore BDT.
* Tender Security can be maximum 3% of Official Cost Estimate. So estimated cost is more than Tk. 16666666.
* Tender Security is normally more than 1% of Official Cost Estimate. So estimated cost should be less than 50000000 BDT.
Thus, Official Cost Estimate should be BDT. 16666666 ~ 20000000.

Eligibility criteria:
1. All the tenderers must be registered with the e-GP portal through CPTU.
2. The tenderer should meet all of the criteria outlined in the TDS.
3. Tenderers should submit their credit line facility/Liquid assets certificate according to the attached format (Form PW2a-3). The credit line facility certificate format is attached in section 7 in TDS. Without a credit line facility/Liquid assets certificate according to the attached format, the tenderer may be declared as non-responsive.
4. The quoted amount of the tender beyond 10% above/less than the official estimated cost will be non-responsive.
5. Payments of executed work will be made upon the availability of funds. Any claim for the late payments will not be entertained. The quality & quantity of work shall be checked by the BWDB Task Force Committee.
6. The Contractor shall keep records of still and video pictures of the works before and after the completion of the works, at his own expense, maintaining the same angle of pictures.
7. After completion of the tender opening process, if the authority is unable to download important documents from the tender that are considered for tender evaluation, the tenderer may be treated as non-responsive.
8. The works will be implemented as deposit work funded by CEIP-1. The payment shall be made upon joint certification of BWDB officials, Bagerhat, representatives of DDCS & PMS consultant, CEIP-1 and PMU, CEIP-1, Dhaka. The contractor must comply with all the terms and conditions of the Memorandum of Understanding (MoU) signed between Bagerhat O&M Division and the Project Director, PMU, CEIP-1, Dhaka.
9. The works must be completed within the stipulated time. There is no scope for time extension as the Project will be closed on December 2023.
Executive Engineer
Bagerhat O&M Division
BWDB, Bagerhat.
Location of work / delivery: Bagerhat
Budget Type: Revenue
Category: Construction work for water projects; Works for complete or part construction and civil engineering work;
PE Address: Bagerhat, City: Bagerhat, Thana: Bagerhat Sadar, District: Bagerhat - 9300, Country: Bangladesh,
See live tender notices for embankment.
Share on Twitter