Login |Register

LTM tenders of Satkhira district. | OSTETM tenders of Satkhira zilla. | OTM tenders of Satkhira. | View All the active tenders of Satkhira district.

eGP Tender ID: 835775; Works (NCT)
APP ID: 190704; District: Satkhira
Reference No.: 1T-4/2875, Date: 21/05/2023
Package Title: Slope protection work with rehabilitation of Embankment work at 9 no sora in between km 3.920 to km 5.680 = 1.59 4 km in Polder No. 15 under " Rehabilitation of polder-15 at Satkhira District" under Satkhira O&M Division-1, BWDB, Satkhira during the year 2022-23.
Organization: Bangladesh Water Development Board (BWDB)
Procuring Entity: Satkhira O&M Division-1
Procurement Method: Open Tendering Method (OTM)
IFT Published on: 2023-05-22 12:00:00
Document last selling: 2023-06-19 17:00:00
Closing / Opening: 2023-06-20 13:00:00
Brief Description of Package: W Sat-1/29
Slope protection work with rehabilitation of Embankment work at 9 no sora in between km 3.920 to km 5.680 = 1.594 km in Polder No. 15 under " Rehabilitation of polder-15 at Satkhira District" under Satkhira O&M Division-1, BWDB, Satkhira during the year 2022-23.
Tender Document Price: Tk. 4000; Tender Security: 5000000 BDT
Official Cost Estimate (Prediction):
* Since document price is Tk. 4000, estimated cost should be more than 2 crore BDT.
* Tender Security can be maximum 3% of Official Cost Estimate. So estimated cost is more than Tk. 166666666.
* Tender Security is normally more than 1% of Official Cost Estimate. So estimated cost should be less than 500000000 BDT.
Thus, Official Cost Estimate should be BDT. 166666666 ~ 500000000.

Eligibility criteria:
Criteria for Eligible contractor:
All the egp enlisted contractor satisfying the criteria mentioned in e-PW3 document attached herewith as per PPA-2006 and latest PPR-2008. The following conditions are applicable:
Payment of work will be made on availability of budget & fund release. No extra claim/ interest for delaying in payment will be entertained. R/A bill will be entertained on the availability of budget and fund. But work progress will not be hampered for lack of fund release/ want of R/A Bill.
Latest Technical specification for civil work of BWDB will govern provided in particular specifications.
The design may be changed/altered/revised (if required) and quantity of tender item may be increased or decreased.
Prework & Postwork will be taken by Taskforce and BWDB’s concern engineer in charge. Final Payment will be made on the measurement taken by Taskforce.
The selected contractor will handover total work site at a time. No scope to handover the site partly.
The all the conditions are specified in separate sheet attached in General specifications
Taskforce guideline of BWDB will govern enclosed in General specifications.
Project: Rehabilitation of Polder No. 15 in Satkhira District
Location of work / delivery: Shyamnagar, Satkhira
Budget Type: Development
Category: Construction work for water projects; Works for complete or part construction and civil engineering work;
PE Address: Satkhira, City: Satkhira, Thana: Satkhira Sadar, District: Satkhira - 9400, Country: Bangladesh,


See more tenders from Satkhira O&M Division-1; Bangladesh Water Development Board (BWDB):
982440 : W Sat-1/44 Construction of Drainage Cum Flushing Regulator 3-Vent (1.50mx1.80m) on Chakbara Khal at km 27.490 in polder no-15 under the project "Rehabilitation of polder no. 15 in Satkhira District" during the FY 2023-24.
982439 : W Sat-1/43 Construction of 2-Vent(1.50mx1.80m) Regulator at Chadnimukha Khal km 6.515 & 2-Vent (1.50mx1.80m) Regulator at Gabura Khal km 20.830 in polder no-15 under the project "Rehabilitation of polder no. 15 in Satkhira District" during the FY 2023-24.
982437 : W Sat-1/42 Construction of 1-Vent Regulator at 9 no. Sora Khal km 2.847 & 1-Vent Regulator at Dumuria Khal km 28.550 in polder no-15 under the project "Rehabilitation of polder no. 15 in Satkhira District" during the FY 2023-24.
979032 : W Sat-1/27 Re-Excavation of Majumder khal from ch. Km 0.000 to km 16.080= 16.080 km & Majumder Branch khal from ch. Km 0.000 to km 0.900 = 0.900 km Total 16.980 Km at Satkhira District.
975427 : W Sat-1/33/2023-24 Permanent Slope protection work with Rehabilitation of Embankment of length 0.800 km in between km 12.250 to km 13.500 of Polder No. 15 at Parshemari under "Rehabilitation of polder-15 in Satkhira District" Project.
975426 : W Sat-1/32/2023-24 Permanent Slope protection work with Rehabilitation of Embankment of Length 1.030 km in between km 10.750 to km 12.250 of Polder No. 15 at Parshemari under "Rehabilitation of polder-15 in Satkhira District" Project.
See live tender notices for embankment.
Share on Twitter