eGP Tender ID: 814579; Works (NCT)
APP ID: 189409; District: Jhalakathi
Package Title: Precautionary Protection Work at the Right Bank of Sugandha River from Km. 29.700 to Km. 29.796 = 96 m & from Km. 30.145 to Km. 30.450 = 305 m; Total = 401 m at Magar of Nalcity Upazilla in Jhalakathi District during the FY 2022-23.
Organization: Bangladesh Water Development Board (BWDB)
Procuring Entity: Jhalokathi WD Division
Procurement Method: Open Tendering Method (OTM)
IFT Published on: 2023-04-09 16:30:00
Document last selling: 2023-04-30 17:00:00
Closing / Opening: 2023-05-01 13:00:00
Brief Description of Package: Jhal/NDR/PBPW/22-23/W-27
Precautionary Protection Work at the Right Bank of Sugandha River from Km. 29.700 to Km. 29.796 = 96 m & from Km. 30.145 to Km. 30.450 = 305 m; Total = 401 m at Magar of Nalcity Upazilla in Jhalakathi District during the FY 2022-23.
Tender Document Price: Tk. 4000; Tender Security: 700000 BDT
Official Cost Estimate (Prediction):
* Since document price is Tk. 4000, estimated cost should be more than 2 crore BDT.
* Tender Security can be maximum 3% of Official Cost Estimate. So estimated cost is more than Tk. 23333333.
* Tender Security is normally more than 1% of Official Cost Estimate. So estimated cost should be less than 70000000 BDT.
Thus, Official Cost Estimate should be BDT. 23333333 ~ 70000000.

Eligibility criteria:
(A) The Tenderer shall submit with its Tender the following additional documents:
1) Valid Trade Licence, TIN number, VAT Registration, Nationality (NID) & Business address, Declaration about legal capacity toenter in to the contract.
2) Work plan, Statement of work method, Equipment & Personnel.
(B) Special Instruction:
1) The work of the package may be totally dropped, decreased or increased as per field condition/design/administrativeapproval/budget allocation for which no claim will be entertained for cancellation of the tender/Issuance of work order.
2) Payment will be made subject to the availability of fund. No claim in this regard will be entertained.
3) Continuation of work could not be hampered by the bidder showing the cause of insufficient Budget Provision & Fund Allocation.The work must be completed within the stipulated time.
4) If the Tenderer(s) submit(s) any false/incorrect/forged certificate or try to hide ongoing work/commitment Purposefully, the tenderwill be outright rejected and action as per PPR-2008 will be initiated.
5) The Procuring entity reserves the right to accept or reject any or all Tenders without assigning any reason whatsoever.
6) Letter of Commitment for Bank’s Undertaking for Line of Credit must be submitted in the specific form (Form PW2a-3) (Enclosein General Specification). Otherwise Tender will be non-responsive.
7) Latest circular of CPTU and CPC of BWDB shall be implied.
8) The work has no fund allocation in 2022-23 FY under Jhalokathi WD Division, BWDB's O&M Budget. 
Location of work / delivery: Magar of Nalcity Upazilla in Jhalakathi District
Budget Type: Revenue
Category: Works for complete or part construction and civil engineering work; Construction work; Building construction work; Engineering works and construction works; Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork; Construction work for water projects; Construction works for plants, mining and manufacturing and for buildings relating to the oil and gas industry; Roof works and other special trade construction works
PE Address: Jhalokathi, City: Jhalokathi, Thana: Jhalokathi Sadar, District: Jhalokathi - 8400, Country: Bangladesh,


See more tenders from Jhalokathi WD Division; Bangladesh Water Development Board (BWDB):
980343 : JHAL/W-09/2023-24 River Bank Protection Work along the left bank of the Shugandhya River from Km 33.140 to Km. 33.510 = 0.370 Km at Nalcity Municipality in Jhalakathi in c/w "River bank protective work at different places of Jhalakathi Sadar and Nalcity upazilla of Jhalakathi district from the erosion of Shugandha River" District under Jhalakathi WD Division, BWDB, Jhalakathi.
968230 : JHAL/W-20/2023-24 River Bank Protection Work at Right Bank of Shugandha River from km. 40.755 to km. 40.947 = 0.192 Km at Basanda Union in Jhalakathi Sadar Upazila in C/W " River bank protective work at different places of Jhalakathi Sadar and Nalcity upazilla of Jhalakathi district from the erosion of Shugandha river"Under Jhalakathi WD Division, BWDB, Jhalakathi.
968229 : JHAL/W-19/2023-24 River Bank Protection Work at Right Bank of Shugandha River from km. 40.350 to km. 40.560 = 0.210 Km at Kutubnagar of Jhalakathi Municipality in Jhalakathi Sadar Upazila in C/W " River bank protective work at different places of Jhalakathi Sadar and Nalcity upazilla of Jhalakathi district from the erosion of Shugandha river" Under Jhalakathi WD Division, BWDB, Jhalakathi.
968228 : JHAL/W-18/2023-24 River Bank Protection Work at Right Bank of Shugandha River from km. 39.900 to km. 40.350 = 0.450 Km at Kutubnagar of Jhalakathi Municipality in Jhalakathi Sadar Upazila in C/W "River bank protective work at different places of Jhalakathi Sadar and Nalcity upazilla of Jhalakathi district from the erosion of Shugandha river" Under Jhalakathi WD Division, BWDB, Jhalakathi.
967603 : JHAL/W-10/2023-24 River Bank Protection Work along the left bank of the Shugandha River from Km. 33.510 to Km. 33.880 = 0.370 Km at Nalcity Municipality in Jhalakathi District in c/w "River bank protective work at different places of Jhalakathi Sadar and Nalcity upazilla of Jhalakathi district from the erosion of Shugandha River" under Jhalakathi WD Division, BWDB, Jhalakathi.
967602 : JHAL/W-11/2023-24 River Bank Protection Work along the left bank of the Shugandha River from Km 33.880 to Km. 34.250 = 0.370 Km at Nalcity Municipality in Jhalakathi District in c/w "River Bank Protective Work at different places of Jhalakathi Sadar and Nalcity upazilla of Jhalakathi district from the erosion of Shugandha River" under Jhalakathi WD Division, BWDB, Jhalakathi.