eGP Tender ID: 1106648; Works (NCT)
APP ID: 204392;
District: Khulna
Reference No.: T-2/1758, Dated- 04-05-2025
Package Title: Emergency precautionary re-sectioning work of Embankment from Km. 3.000 to Km. 3.300 Total 300 m. in Polder No.17/1 at Gazinagar, Upazila: Dumuria, District: Khulna under O&M budget of Khulna WD Division-1, BWDB, Khulna during the year 2024-25.
Organization: Bangladesh Water Development Board (BWDB)
Procuring Entity: Khulna WD Division-1
Procurement Method: Open Tendering Method (OTM)
IFT Published on: 2025-05-04 14:25:00
Document last selling: 2025-05-15 11:00:00
Closing / Opening: 2025-05-15 13:20:00
Brief Description of Package: Emergency precautionary re-sectioning work of Embankment from Km. 3.000 to Km. 3.300 Total 300 m. in Polder No.17/1 at Gazinagar, Upazila: Dumuria, District: Khulna under O&M budget of Khulna WD Division-1, BWDB, Khulna during the year 2024-25.
Tender Document Price: Tk. 1000;
Tender Security: 20000 BDT
Official Cost Estimate (Prediction):
* Since document price is Tk. 1000, estimated cost should be less than or equal 50 lacs BDT.
* Tender Security can be maximum 3% of Official Cost Estimate. So estimated cost is more than Tk. 666666.
* Tender Security is normally more than 1% of Official Cost Estimate. So estimated cost should be less than 2000000 BDT.
Thus, Official Cost Estimate should be BDT. 666666 ~ 2000000.
Eligibility criteria:
1. All tenderer registered in e-gp portal system are eligible.
2. Detail Turnover Calculation sheet mentioning the Name of Work, PE name etc (Year wise over the last five years) duly signed by the Tenderer must be submitted with the tender.
3. Payment will be made upon availability of fund. For this, no claim will be entertained.
4. Quoted amount of tenderer beyond 10% above/less than official estimated cost will be non-responsive.
5) The tenderer MUST submit the Line of Credit from any scheduled bank of Bangladesh in the specified supplied format. (Copy supplied, See sec-8)
6) It is the duty of the tenderer to submit all the documents freshly (Without Corrupted). If any documents get corrupted and the evaluation team could not be able to open the file, no claim from the tenderer regarding the file will be entertained.
7) VAT & IT from bill will be as per prevailing Government Rate. No extra claim will be entertained in this regard.
8) Evaluation will be done following the latest Gazette/Circular from CPTU.
9) If any type of Structures/Obstacles is needed to dismantle to execute the Re-Excavation work as per Design and Specification, the bidder will do this at his own cost and arrangement. No extra claim will be entertained in this regard.
10) The tenderer must submit his documents following the latest instructions and formats of CPTU.
11) If BWDB Owned land is not sufficient to execute the work as per design and Specification, The bidder will do this at his own cost and arrangement.
12) It is mandatory for the tenderer to submit video and still photographs of the said work in pre-work condition and post work condition. (Circular copy supplied, See sec-8)
13) Work order will be issued after getting approval from BWDB authority.
14) PE reserve the right to cancel/modify the tender any time.
Location of work / delivery: Dumuria, Khulna
Budget Type: Revenue
Category: Construction work for water projects; Works for complete or part construction and civil engineering work;
PE Address: Noor Nagar, Khulna, City: Khulna, Thana: Khulna City Corporation, District: Khulna - 9000, Country: Bangladesh,
See more tenders from
Khulna WD Division-1; Bangladesh Water Development Board (BWDB):
1205724 : Khulna-1/Salta/2025-2/W-09
Repair work of Bakultola Regulator in connection with the project Re-excavation of Salta River for mitigation of pollution, eviction of illegal Structures & Rejuvenation of Salta River under Khulna District under Khulna Water Development Division-1, BWDB, Khulna.
1205387 : Khulna-1/Salta/2025-2/W-03
Re-excavation of Tiabunia Khal from Km.0.000 to Km. 1.700 = 1.700 Km. in connection with the project Re-excavation of Salta River for mitigation of pollution, eviction of illegal Structures & Rejuvenation of Salta River under Khulna District under Khulna Water Development Division-1, BWDB, Khulna.
1205386 : Khulna-1/Salta/2025-2/W-04
Re-excavation of Shostitola Khal from Km.0.000 to Km. 1.500 = 1.500 Km. in connection with the project Re-excavation of Salta River for mitigation of pollution, eviction of illegal Structures & Rejuvenation of Salta River under Khulna District under Khulna Water Development Division-1, BWDB, Khulna.
1205385 : Khulna-1/Salta/2025-2/W-07
Re-excavation of Kanaidanga Khal from Km.0.000 to Km. 2.000 = 2.000 Km. in connection with the project Re-excavation of Salta River for mitigation of pollution, eviction of illegal Structures & Rejuvenation of Salta River under Khulna District under Khulna Water Development Division-1, BWDB, Khulna.
1203387 : Khulna-1/NDR/2025-26/W-02
Conducting survey works in c/w Polder no.-25, 27/1, 28/1, 28/2 and Barakpur-Dighalia Project in District: Khulna under operation budget of Khulna WD Division-1, BWDB, Khulna during the year 2025-2026.
1203385 : Khulna-1/NDR/2025-26/W-04
Re-excavation of Baloijhaki Sakha Bai Khal from Km 0.000 to Km 2.650 = 2.650Km in Polder No. 26 at Baloijhaki, Dumuria-upazila, District-Khulna under Khulna WD Division-1, BWDB, Khulna Under Operation & Expenditure Budget during the year 2025-26.