Login |Register

LTM tenders of Khulna district. | OSTETM tenders of Khulna zilla. | OTM tenders of Khulna. | View All the active tenders of Khulna district.

eGP Tender ID: 1106648; Works (NCT)
APP ID: 204392; District: Khulna
Reference No.: T-2/1758, Dated- 04-05-2025
Package Title: Emergency precautionary re-sectioning work of Embankment from Km. 3.000 to Km. 3.300 Total 300 m. in Polder No.17/1 at Gazinagar, Upazila: Dumuria, District: Khulna under O&M budget of Khulna WD Division-1, BWDB, Khulna during the year 2024-25.
Organization: Bangladesh Water Development Board (BWDB)
Procuring Entity: Khulna WD Division-1
Procurement Method: Open Tendering Method (OTM)
IFT Published on: 2025-05-04 14:25:00
Document last selling: 2025-05-15 11:00:00
Closing / Opening: 2025-05-15 13:20:00
Brief Description of Package: Emergency precautionary re-sectioning work of Embankment from Km. 3.000 to Km. 3.300 Total 300 m. in Polder No.17/1 at Gazinagar, Upazila: Dumuria, District: Khulna under O&M budget of Khulna WD Division-1, BWDB, Khulna during the year 2024-25.
Tender Document Price: Tk. 1000; Tender Security: 20000 BDT
Official Cost Estimate (Prediction):
* Since document price is Tk. 1000, estimated cost should be less than or equal 50 lacs BDT.
* Tender Security can be maximum 3% of Official Cost Estimate. So estimated cost is more than Tk. 666666.
* Tender Security is normally more than 1% of Official Cost Estimate. So estimated cost should be less than 2000000 BDT.
Thus, Official Cost Estimate should be BDT. 666666 ~ 2000000.

Eligibility criteria:
1. All tenderer registered in e-gp portal system are eligible.
2. Detail Turnover Calculation sheet mentioning the Name of Work, PE name etc (Year wise over the last five years) duly signed by the Tenderer must be submitted with the tender.
3. Payment will be made upon availability of fund. For this, no claim will be entertained.
4. Quoted amount of tenderer beyond 10% above/less than official estimated cost will be non-responsive.
5) The tenderer MUST submit the Line of Credit from any scheduled bank of Bangladesh in the specified supplied format. (Copy supplied, See sec-8)
6) It is the duty of the tenderer to submit all the documents freshly (Without Corrupted). If any documents get corrupted and the evaluation team could not be able to open the file, no claim from the tenderer regarding the file will be entertained.
7) VAT & IT from bill will be as per prevailing Government Rate. No extra claim will be entertained in this regard.
8) Evaluation will be done following the latest Gazette/Circular from CPTU.
9) If any type of Structures/Obstacles is needed to dismantle to execute the Re-Excavation work as per Design and Specification, the bidder will do this at his own cost and arrangement. No extra claim will be entertained in this regard.
10) The tenderer must submit his documents following the latest instructions and formats of CPTU.
11) If BWDB Owned land is not sufficient to execute the work as per design and Specification, The bidder will do this at his own cost and arrangement.
12) It is mandatory for the tenderer to submit video and still photographs of the said work in pre-work condition and post work condition. (Circular copy supplied, See sec-8)
13) Work order will be issued after getting approval from BWDB authority.
14) PE reserve the right to cancel/modify the tender any time.
 
Location of work / delivery: Dumuria, Khulna
Budget Type: Revenue
Category: Construction work for water projects; Works for complete or part construction and civil engineering work;
PE Address: Noor Nagar, Khulna, City: Khulna, Thana: Khulna City Corporation, District: Khulna - 9000, Country: Bangladesh,


See more tenders from Khulna WD Division-1; Bangladesh Water Development Board (BWDB):
1106656 : OTM-Khulna-109-2024-2025 Supplying, Filling and Placing/Dumping of Polyestar made 175 kg Geo-Textile bags for emergency meet up of upcoming flood under O&M Budget of Khulna WD Division-1, BWDB, Khulna during the year 2024-25.
1106655 : OTM-Khulna-108-2024-2025 Emergency re-excavation & silt removal work of Kaderia Khal from Km. 0.000 to Km. 0.400 = 0.400 Km & Km. 1.725 to Km. 2.050 = 0.325 Total 0.725 Km. in Polder No.28/1 at Upazila: Dumuria, District: Khulna under O&M budget of Khulna WD Division-1, BWDB, Khulna during the year 2024-25.
1106654 : OTM-Khulna-107-2024-2025 Emergency precautionary temporary protective work along the left bank of Rupsha River in between km.5.100 to km. 5.510= 0.085 Km at Rahimnagar Bazar, Upazila: Rupsha, District: Khulna under O&M budget of Khulna WD Division-1, BWDB, Khulna during the year 2024-25.
1106653 : OTM-Khulna-106-2024-2025 Emergency precautionary temporary protective work along the right bank of Gangrail River in between km.27.550 to km. 27.600 =50.00m in Polder No.29 at Shambunagar, Upazila: Batiaghata, District: Khulna under O&M budget of Khulna WD Division-1, BWDB, Khulna during the year 2024-25.
1106652 : OTM-Khulna-105-2024-2025 Emergency precautionary temporary protective work along the right bank of Bhadra River from Km. 21.630 to Km. 21.650 total 20 m. in Polder No.29 at Chadghar, Upazila: Dumuria, District: Khulna under O&M budget of Khulna WD Division-1, BWDB, Khulna during the year 2024-25.
1106651 : OTM-Khulna-104-2024-2025 Emergency precautionary re-sectioning work of Embankment from Km. 8.700 to Km. 10.000 total 1300 m. in Polder No.17/2 at Boratia, Upazila: Dumuria, District: Khulna under O&M budget of Khulna WD Division-1, BWDB, Khulna during the year 2024-25.
See live tender notices for embankment.
Share on Twitter