LTM tenders of Bagerhat district. |
OSTETM tenders of Bagerhat zilla. |
OTM tenders of Bagerhat. |
View All the active tenders of Bagerhat district.
eGP Tender ID: 1078816; Works (NCT)
APP ID: 206952;
District: Bagerhat
Reference No.: 42.01.0100.617.44.001.24-638; 20-02-2025
Package Title: Re-excavation of Aruyarber khal from km 0.000 to km 8.200 = 8.200 km at Dhansagor, Chandpai Range in C/W "Protection of Sundarbans Mangrove Forest project (1st Revised)" of Bangladesh Forest Department in Bagerhat District under Bagerhat WD Division, BWDB, Bagerhat.
Organization: Bangladesh Water Development Board (BWDB)
Procuring Entity: Bagerhat WD Division
Procurement Method: Open Tendering Method (OTM)
IFT Published on: 2025-02-23 12:00:00
Document last selling: 2025-03-17 11:30:00
Closing / Opening: 2025-03-17 13:00:00
Brief Description of Package: BH/W-02
Re-excavation of Aruyarber khal from km 0.000 to km 8.200 = 8.200 km at Dhansagor, Chandpai Range in C/W "Protection of Sundarbans Mangrove Forest project (1st Revised)" of Bangladesh Forest Department in Bagerhat District under Bagerhat WD Division, BWDB, Bagerhat.
Tender Document Price: Tk. 4000;
Tender Security: 1230000 BDT
Official Cost Estimate (Prediction):
* Since document price is Tk. 4000, estimated cost should be more than 2 crore BDT.
* Tender Security can be maximum 3% of Official Cost Estimate. So estimated cost is more than Tk. 41000000.
* Tender Security is normally more than 1% of Official Cost Estimate. So estimated cost should be less than 123000000 BDT.
Thus, Official Cost Estimate should be BDT. 41000000 ~ 123000000.
Eligibility criteria:
1. All the tenderers must be registered with e-GP portal through CPTU.
2. Tenderer should fulfill all criteria's which are stated in TDS.
3. Tenderer should submit their credit line facility/Liquid assets certificate according to attached format (Form PW3-7). Credit line facility certificate format is attached in section-7 in TDS. Without credit line facility/Liquid assets certificate according to attached format tender declare as non-responsive.
4. Quoted amount of tender beyond 10% above/less than official estimated cost will be non- responsive.
5. The site of Re-excavation works is not acquired land of BWDB. No claim or compensation shall be entertained in this connection.
6. Payments of executed work will be made upon availability of funds. Any claim for the late payments will not be entertained. Quality & quantity of works shall be checked by BWDB Task Force Committee.
7. Confirming the circular about Formation of JVCA, Business Share, Specific Experience, Turnover (See attached document of CPTU Circular in section 8: Particular Specification).
8. The Contractor shall keep records of steal and video pictures of the works before start of work and after completion of works maintaining same angle of pictures at his own cost.
9. After completion the tender opening process, if disable to downloading important documents of the tender, which consider to tender evaluation. In order to the tender may be treated as non-responsive.
Executive Engineer
Bagerhat WD Division
BWDB, Bagerhat.
Location of work / delivery: Dhansagor, Bagerhat
Budget Type: Revenue
Category: Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork; Works for complete or part construction and civil engineering work;
PE Address: Bagerhat, City: Bagerhat, Thana: Bagerhat Sadar, District: Bagerhat - 9300, Country: Bangladesh,
See more tenders from
Bagerhat WD Division; Bangladesh Water Development Board (BWDB):
1253776 : Bag/Rev/W-40/2025-26
Repair of Rain Cuts and Rat Holes on Embankment Top and Slopes from km 14.200 to km 25.200= 11.000 km of Polder No: 35/1 in Bagerhat District under Operational Expenditure Budget of Bagerhat WD Division, BWDB, Bagerhat during the FY 2025-2026.
1253281 : Bag/Rev/W-39/2025-26
Survey Works of River/Khal/Embankment of Various Projects in Polder no-34/1, Polder no-35/3 & Najirpur sub-Project under Bagerhat WD Division, BWDB, Bagerhat under Operational Expenditure Budget during the FY 2025-26.
1204079 : BH/W-03
Dredging of Bhola River from km 0.000 to km 3.850=3.850 km at Dhansagor, Chandpai Range in C/W 'Protection of Sundarbans Mangrove Forest project (1st Revised)' of Bangladesh Forest Department in Bagerhat District under Bagerhat WD Division, BWDB, Bagerhat.
1194915 : Bag/Rev//W-35/2025-26
Precautionary Protective Work along the right bank of Bhairab River at Chinteirkhor from Km 0.000 to Km 0.100 & Km 0.200 to Km 0.300 = 200.00m in Polder No-36/1 at Bagerhat Sadar Upazila in Bagerhat district under Bagerhat WD Division, BWDB, Bagerhat during the FY 2025-2026.
1194911 : Bag/Rev//W-23/2025-26
Temporary Slope Protection work from km 7.050 to km 7.200 = 150 m & from km 7.750 to km 8.100 = 350.00 m, Total = 500.00 m at vodropara under Bemorta Sub-project along the L/B of Daratana River in Bemorta Union, Bagerhat Sadar Upazilla under Bagerhat WD Division, BWDB, Bagerhat during the year 2025-2026.
1194902 : Bag/Rev/W-27/2025-26
Repair of Bank Protection work from km 0.400 to km 0.530 = 130.00 m at Rahimabad along the R/B of Bhairob River in Karapara Union, Bagerhat Sadar Upazilla under Bagerhat WD Division, BWDB, Bagerhat during the year 2025-2026.