Login |Register

LTM tenders of Barguna district. | OSTETM tenders of Barguna zilla. | OTM tenders of Barguna. | View All the active tenders of Barguna district.

eGP Tender ID: 1048173; Works (NCT)
APP ID: 209367; District: Barguna
Reference No.: Barguna/MQ-52/1837, Date: 08-12-2024
Package Title: Repair of embankment at Gudighata from km 64.250 to km 64.595 = 0.345 km in Polder No. 39/1D under NDR Budget at Barguna WD Division, BWDB, Barguna during the FY 2024-2025.
Organization: Bangladesh Water Development Board (BWDB)
Procuring Entity: Barguna WD Division
Procurement Method: Open Tendering Method (OTM)
IFT Published on: 2024-12-09 12:00:00
Document last selling: 2024-12-23 16:00:00
Closing / Opening: 2024-12-24 12:00:00
Brief Description of Package: Repair of embankment at Gudighata from km 64.250 to km 64.595 = 0.345 km in Polder No. 39/1D under NDR Budget at Barguna WD Division, BWDB, Barguna during the FY 2024-2025 (BR-NDR-05/2024-2025).
Tender Document Price: Tk. 1000; Tender Security: 24500 BDT
Official Cost Estimate (Prediction):
* Since document price is Tk. 1000, estimated cost should be less than or equal 50 lacs BDT.
* Tender Security can be maximum 3% of Official Cost Estimate. So estimated cost is more than Tk. 816666.
* Tender Security is normally more than 1% of Official Cost Estimate. So estimated cost should be less than 2450000 BDT.
Thus, Official Cost Estimate should be BDT. 816666 ~ 2450000.

Eligibility criteria:
a) Tenderer must be registered in the e-GP portal through CPTU along with validband updated Trade License, Vat Registration and
TIN certificate.
b) Quoted amount of tenderer beyond 10% above/less than official estimated cost will be non- responsive.
c) It is duty of contractor to submit all the documents freshly (without corrupted). If any documents get corrupted and evaluation
committee could not able to open the file, no claim from the tenderer will be entertained regarding the file.
d) Vat & IT will be deducted as per the prevailing government rate. No extra claim will be entertained in this regard.
e) Tender evaluation will be done following the latest gazette /circular from CPTU.
f) A detailed list of work in hand /ongoing works duly signed by the tenderer must be submitted.
g) If any kind of obstacles/structures is needed to dismantle to execute the work as per design and specification the tenderer will
do this at his/her own arrangement and cost. No extra claim will be entertained in this regard.
h) If BWDB owned/acquired land is not sufficient to execute the work as per design and specification the tenderer will do this at
his/her own arrangement and cost.
i) Photo and video must have to be taken by the contractor at a different angle during prework and post-work measurement and
submitted to the PE. No extra claim will be entertained in this regard.
j) All other criteria stated in the tender document.
k) Detail turnover calculation sheet and Ongoing work mentioning the name of work, PE name etc. (year wise over the last five
years) duly signed by the Tenderer must be submitted with the tender.
 
Location of work / delivery: Bamna, Barguna
Budget Type: Revenue
Category: Construction work for water projects; Works for complete or part construction and civil engineering work;
PE Address: Barguna, City: Barguna, Thana: Barguna Sadar, District: Barguna - 8700, Country: Bangladesh,


See more tenders from
Notice: Undefined index: PEID in /home/dorpatra/public_html/getEGPNotice.php on line 197
Barguna WD Division; Bangladesh Water Development Board (BWDB)
:
1230448 : ATKRW-06 Removal of water hyacinth of Subondi khal from km 0.000 to km 15.000=15.000 km under polder 43/1 in c/w "Rehabilitation of Polder 43/1 and 44B and protection of vulnerable portion from erosion of the Payra River under Barguna District (1st Revised)" project under Barguna WD Division, BWDB, Barguna during FY 2025-2026.
1220510 : BTBPW-15/2022-23/Remaining Slope protection of embankment and riverbank protective work at Fuljhuri Launch Ghat under Polder 41/6B from Km 19.200 to Km 19.450 = 0.250 Km in connection with "Rehabilitation of Polder 41/6A, 41/6B & 41/7A and protection of vulnerable portion including Betagi town from the erosion of Bishkhali & Payra river under Barguna district" under Barguna WD Division, BWDB, Barguna (BTBPW-15/2022-23/Remaining)
1220509 : BTBPW-20/2022-23/Remaining Slope protection of embankment and river bank protective work at jangalia under Polder 41/6A from Km 4.150 to Km 4.400 = 0.250 Km in connection with Rehabilitation of Polder 41/6A, 41/6B & 41/7A and protection of vulnerable portion including Betagi town from the erosion of Bishkhali & Payra river under Barguna district under Barguna WD Division, BWDB, Barguna (BTBPW-20/2022-23/Remaining)
1220508 : BTBPW-18/2022-23/Remaining Slope protection of embankment and riverbank protective work at Fuljhuri Launch Ghat under Polder 41/6B from Km 20.000 to Km 20.315 = 0.315 Km in connection with Rehabilitation of Polder 41/6A, 41/6B & 41/7A and protection of vulnerable portion including Betagi town from the erosion of Bishkhali & Payra river under Barguna district.under Barguna WD Division, BWDB, Barguna. (BTBPW-18/2022-23/Remaining)
1203556 : BR-NDR-10/2025-26 Re-sectioning of Embankment with Precautionary Slope Protection work and Precautionary River Bank Protection work on the Right Bank of the Payra River from km. 7.725 to km. 7.858 = 0.133 km in Polder No: 41/5 at Choto Baliatali, Barguna Sadar Upazila under Barguna WD Division, BWDB, Barguna during the year 2025-2026.
1137446 : BR-NDR-03/2025-26 Re-excavation of Jintala Khal from km 0.00 to km 2.200 total 2.200 km in Polder no-41/6B under Barguna WD Division, BWDB, Barguna During the FY 2025-2026.
See live tender notices for embankment.
Share on Twitter