Login |Register

LTM tenders of Moulvibazar district. | OSTETM tenders of Moulvibazar zilla. | OTM tenders of Moulvibazar. | View All the active tenders of Moulvibazar district.

eGP Tender ID: 1075193; Works (NCT)
APP ID: 205087; District: Moulvibazar
Reference No.: DA-1/1419 dt: 16/02/2025
Package Title: Re-excavation Work of Khaspremnagar Khal from km. 0.000 to 1.500 = 1500.00m at Kamarchak UP; Rajnagar Upazila Under Moulvibazar District under Non-Development Revenue Budget (Code-3258137) under Moulvibazar WD Division, BWDB, Moulvibazar during the Financial year 2024-25.
Organization: Bangladesh Water Development Board (BWDB)
Procuring Entity: Moulvibazar WD Division
Procurement Method: Open Tendering Method (OTM)
IFT Published on: 2025-02-17 10:30:00
Document last selling: 2025-03-03 17:00:00
Closing / Opening: 2025-03-04 12:00:00
Brief Description of Package: MOULV/NDR/2024-25/W-38
Re-excavation Work of Khaspremnagar Khal from km. 0.000 to 1.500 = 1500.00m at Kamarchak UP; Rajnagar Upazila Under Moulvibazar District under Non-Development Revenue Budget (Code-3258137) under Moulvibazar WD Division, BWDB, Moulvibazar during the Financial year 2024-25.
Tender Document Price: Tk. 1000; Tender Security: 100000 BDT
Official Cost Estimate (Prediction):
* Since document price is Tk. 1000, estimated cost should be less than or equal 50 lacs BDT.
* Tender Security can be maximum 3% of Official Cost Estimate. So estimated cost is more than Tk. 3333333.
* Tender Security is normally more than 1% of Official Cost Estimate. So estimated cost should be less than 10000000 BDT.
Thus, Official Cost Estimate should be BDT. 3333333 ~ 5000000.

Eligibility criteria:
Special Instructions:
01. Only e-GP registered Tenderer/Firms can participate to the Tender.
02. Tenderer should fulfill all criterias which are stated in TDS.
03. Tenderer should submit their credit line facility/Liquid assets certificate according to attached format (From PW2a-3, in section-7). Without credit line facility/Liquid assets certificate according to attached format tender declare a nonresponsive.
04. Payment will be made upon availability of fund and after Pre & Post work Measurement by BWDBs office & Taskforce team .
05. After completion the tender opening process. If disable to download the important documents of the tender. Which consider to tender evaluation. In order to the tender may be treated as non-responsive.
06. The Tenderers will visit and examine the site with his own responsibility & expenses and obtain all information that may be necessary for preparing the Tender and entering into a Contract for performance of the works.
07. The work of the package may be totally dropped, decreased or increased as per field condition/design/administrative approval/budget allocation for which no claim will be entertained for cancellation of the tender/Issuance of work order.
08. If the Tenderer(s) submit(s) any false/incorrect or forged certificate, the tender will be outright rejected and action as per PPR-2008 will be initiated.
09. Latest circular of CPTU & CPC of BWDB will be followed.
10. The Procuring entity reserves the right to accept or reject any or all Tenders without assigning any reason whatsoever.
Location of work / delivery: Rajnagar
Budget Type: Revenue
Category: Construction work for water projects; Works for complete or part construction and civil engineering work;
PE Address: Moulvibazar., City: Moulvibazar, Thana: Moulvibazar Sadar, District: Moulvibazar - 3200, Country: Bangladesh,


See more tenders from
Notice: Undefined index: PEID in /home/dorpatra/public_html/getEGPNotice.php on line 197
Moulvibazar WD Division; Bangladesh Water Development Board (BWDB)
:
1184383 : MOULV/NDR/2025-26/W-21 Precautionary Bank Protection Work Along the Left Bank of Dhalai River at Dokkhin Gram from km. 38.970 to km. 39.000 = 30 m in C/w Dhalai River Project under Moulvibazar Water Development Division , BWDB, Moulvibazar During the year 2025-26.
1184379 : MOULV/NDR/2025-26/W-20 Precautionary work along the Right Bank of Dhalai River from km 40.100 to km 40.150= 50.00 m at Kushalpur of 3 no Munshibazar Union in Kamalganj Upazilla under NDR Budget of Moulvibazar WD Division, BWDB, Moulvibazar during the year 2025-26.
1184376 : MOULV/NDR/2025-26/W-19 Precautionary work along the Right Bank of Dhalai River from km 38.800 to km 38.910= 110m at Ubahata of 3 no Munshibazar Union in Kamalganj Upazilla under Moulvibazar WD Division, BWDB, Moulvibazar, during the FY 2025-26.
1184373 : MOULV/NDR/2025-26/W-18 Precautionary work along the left Bank of Dhalai River from km 21.300 to km 21.440= 140m at Rampasha of Kamalganj Sadar Union in Kamalganj Upazilla under Moulvibazar WD Division, BWDB, Moulvibazar, during th FY 2025-26.
1184370 : MOULV/NDR/2025-26/W-17 Precautionary Bank protection work at Ghuramara along the R/B of Dhalai river from km 18.270 to km 18.326 = 56.00 m in c/w "Dhalai River project" under Moulvibazar Water Development Division, BWDB, Moulvibazar.
1184366 : MOULV/NDR/2025-26/W-16 Precautionary Bank protection work at Chandpur along the Right bank of Manu River from Km 62.618 to km 62.705 = 87.00 m in c/w "Manu River project" under Moulvibazar W.D. Division, BWDB, Moulvibazar.
Share on Twitter